Lagos-Badagry Expressway: Reps Aggrieved As Contractor Abandons Project

  • CGC Nigeria Ltd abandons Lagos-Badagry Expressway project
  • Reps Vow to invite Fashola over slow pace of work
  • Reps accuses CGC of not taking project seriously at all

The House of Representatives has expressed disappointment that no staff of CGC Nigeria Ltd, the contractor handling Lagos-Badagry Expressway, was on site when its members visited the project on Wednesday.

The House of Representatives Committee on Works, led by its Chairman, Alhaji Abubakar Kabir, was on oversight inspection tour of Agbara and Seme section of Badagry Expressway on Wednesday.

The lawmakers expressed displeasure over lack of commitment of the contractor and vowed to invite the Minister of Works and Housing, Mr Babatunde Fashola, and the contractor over the slow pace of work on the project.

The chairman said it was disheartening that no single expatriate from CGC was on ground to receive the lawmakers to give explanations on construction works.

Read Also: Aggrieved Poly Students Block Lagos-Abeokuta Expressway

“I am highly disappointed with CGC, there is no way, that members of the House of Representatives coming here to Lagos and none of their expatriates are here.

“We have the project worth N63 billion, this is to show CGC are not taking this project seriously at all, this is number one.

“Secondly, the issue of the work we have seen here and the work on the paper, to me, this project is not commensurate with what has been paid,” he said.

Kabir said no mathematical or scientific analysis could generate magical formulas to equate funding to actual construction visible and percentages of level of completion of the projects.

“And you said we have reached about 14.6 per cent completion, even on the average, you have only reached about four per cent and the money we have paid to them (CGC) now is about N6.7 billion.

“N2.2 billion 15 per cent mobilsation, N4.5 billion SUKUK money and that SUKUK money, I don’t understand, there is a problem,” he said.

The chairman said that SUKUK funds were investors’ money and it was dangerous to allow inefficiency or mismanagement, adding that, there was no commensurate construction on ground.

He said it was dangerous for the progress of the nation to entrust projects into the hands of contractors who used COVID-19 as excuse to stay away from site.

“With this, I have to call the minister to come to the National Assembly, the Director, Construction and Rehabilitation, Engineer Funsho Adebiyi, and CGC management to come and discuss. We need to discuss this thing critically.

“Honestly, we are not here for joke, we are here to protect our citizens, we are here to protect taxpayers money, even the SUKUK you are claiming is people’s money, it is investors money and Nigerian government is going to pay for it in future at a higher rate,” he said.

Kabir said about 10 per cent of the contact sum had been paid and if CGC was not serious about the project, “let the government do something about this so that we can get some serious people”.

“Nobody can do this thing in China, nobody; at the end there is no place we can go apart from Nigeria, this is our country,” he said.

Earlier, the Director, Federal Highways, South-West, Mr Adedamola Kuti, said that the project was underfunded until SUKUK funding which were being disbursed based on progress of work.

As a Nigerian, I am not satisfied but the issue is that, it is also funding. If somebody is not paid, there is little I can do, I am not going to give in my blood.

“Like I mentioned to you (lawmakers), an advanced payment of about N9.6 billion was due to the contractor, even to pay N2 billion it took us almost two years, two budgetary provisions or three before the SUKUK funding came in,” he said.

Buttressing his point using graphical drawings on the project board, Kuti explained the extent of construction and drainage works covered by the various stages of the SUKUK funding.

He explained the terms of the contractual agreements and outstanding variations on payment disbursements to the contractor.

YOU MAY ALSO LIKE

Tanker Explosion Kills 2 In Lagos-Abeokuta Expressway

Zainab Balogun

Share
Published by
Zainab Balogun

Recent Posts

Nigerian Govt Declares Public Holidays For Christmas, New Year

The Federal Government has declared Wednesday, Thursday and Jan.1, 2025 as public holidays. This was…

19 minutes ago

‘It’ll Boost Development’ -Matawalle Reacts To Lifting ban On Mining Activities In Zamfara

The Minister of State for Defence, Bello Matawalle, says the lifting of ban on mining…

1 hour ago

Epe Club 50th Anniversary: The Boys Unveil Luxurious Lounge

In a landmark event, Epe Club marked its 50th anniversary with the unveiling of a…

2 hours ago