Lagos-Ibadan Expressway To Be Completed In December – FG

Published

on

Truck Driver Crushes Two To Death While Chasing Car That Damaged His Mirror In Ogun

Lagos-Ibadan Expressway will be completed and totally open to traffic in December, Nigeria’s Coordinating Director, Highway Construction and Rehabilitation, Funsho Adebiyi assures.

Speaking during an inspection tour of the ongoing Lagos-Ibadan Expressway rehabilitation and reconstruction project, Adebiyi said the dual carriageway would be completed.

He added that the bridges would be completed in April 2022.

Recall that Adedamola Kuti, the Director, Federal Highways, South-west had said that by December the entire carriageway would be completed.

Kuti said that the project had reached 49.6 per cent completion on the first section being handled by Julius Berger and 56.8 per cent on the section handled by RCC.

He said that 32 out of 43.6 kilometres of work had been completed and section two which is 84 kilometres has more than 50 kilometres completed on both carriageways.

“This corridor of the Lagos-Ibadan Expressway apart from all the fly overs by the time we are coming to December this year, I think there will be substantial progress .

“Section one is 49.6 per cent completed, section two is 56.8 per cent, so, we are making progress,” he said.

Adebiyi while speaking more on the project, said that the entire dual carriageway would be completed and opened to traffic while work continues on the bridges.

Read Also: Lagos-Ibadan Expressway Accident Kills Six Persons, Leaves Nine Others Injured

“Our plan is that by the end of this year, the entire stretch of the road will be available, the pavement, carriageway will be completed but you have the interchanges before the end of April next year,” he said.

He said discussions were on with the Oyo State Government on Right of Way recovery for reconstruction works to continue around the toll gate area.

While inspecting section two of the highway being constructed by RCC, he said that a thickness of 300mm materials were compressed on various layer to make the road strong and durable.

He said 55km of work was completed on the Ibadan bound lane and 44 km on the Lagos bound carriageway.

Measures were on to ensure that the number of houses to be demolished on the alignment of section one, he said.

He further stated that enumeration of properties on the Right of Way were on to pay compensations.

“Compensation issues are sensitive matters, I am extremely careful in talking about it, but no structure can be demolished except we have evaluated correctly the contents of that structure.

”Again, we confirm the ownership, and we have estate surveyors who have been appointed to go round these houses, evaluate them and report back to us,” he said.




Advertise or Publish a Story on EkoHot Blog:

Kindly contact us at [email protected]. Breaking stories should be sent to the above email and substantiated with pictorial evidence.

Citizen journalists will receive a token as data incentive.

Call or Whatsapp: 0803 561 7233, 0703 414 5611




 

 


DISCLAIMER: Opinion articles are solely the responsibility of the author and does not necessarily reflect the views of the publishers Of  EKO HOT BLOG

For publication of your News Contents, articles, Videos or any other News Worthy Materials, please send to [email protected]

For Advert and other info, you can call 08035617233 or send a WhatsApp Message to 08035617233.

Please drop your comments

Copyright © Ekohotblog

MGID