Third Mainland Bridge: FG Extends Completion, Announces Another Shutdown

Published

on

Third Mainland: FG Extends Completion, Announces Another Shutdown

The Federal Controller of Works in Lagos, Olukayode Popoola Sunday said the Third Mainland Bridge will no longer be opened on Monday but at the end of February.

Popoola told the News Agency of Nigeria (NAN) on the telephone that the bridge would experience one more total closure from Feb. 19 to 21 before completion of the project for the final re-opening by the end of February.

He said; “Third Mainland Bridge will no longer be opened on the 15th of February 2021 as announced earlier on.

“In order not to create untold hardship for the motoring public using the Third Mainland Bridge for their daily activities, the contractor is not allowed to close the Third Mainland Bridge during the week to cast concrete.

“Lane markings on the completed section must be completed.”

Read Also: Third Mainland Bridge: Lagos To Close Oworonshoki-Bound Lane Saturday

“The Federal Ministry of works and Housing regret the inconveniences the extra days may have caused the Lagosians,’’ he added.

Popoola explained that the bridge would be totally shutdown from midnight on Feb. 19 to 21st to cast concrete on the last expansion joint.

He said that the concrete would require between three to four days to set before the final preparations to finally re-open the entire bridge to traffic.

These processes he said could drag to the end of February when the highway would eventually be opened up.

“We are looking at the end of the month for the reopening of the bridge. That is, end of this February.”

He said that work was soon to begin on the casting of the last expansion joint on the bridge before the bridge finally reopens to traffic.

“They will cast concrete on the last expansion joint next week end. We are not allowed to cast during the week so that the traffic will not be too much for people going to work.

“They will cast next weekend and after casting, we need about three or four days to do post-tensioning. That is why we are looking at end of February completion.

“Casting will be done next weekend for the last expansion joint, it will require total closure of the bridge next weekend just to prevent vibration.

“So if we close the bridge Friday night, then we cast on Saturday by Sunday we will open it. That will be the last total closure to fix the last expansion joint,’’ he said.

YOU MAY ALSO LIKE




Advertise or Publish a Story on EkoHot Blog:

Kindly contact us at [email protected]. Breaking stories should be sent to the above email and substantiated with pictorial evidence.

Citizen journalists will receive a token as data incentive.

Call or Whatsapp: 0803 561 7233, 0703 414 5611




 

 


DISCLAIMER: Opinion articles are solely the responsibility of the author and does not necessarily reflect the views of the publishers Of  EKO HOT BLOG

For publication of your News Contents, articles, Videos or any other News Worthy Materials, please send to [email protected]

For Advert and other info, you can call 08035617233 or send a WhatsApp Message to 08035617233.

Please drop your comments

Copyright © Ekohotblog

MGID