Third Mainland Bridge To Reopen At Midnight – Nigerian Govt
- Federal Controller of Works, Lagos, Olukayode Popoola, on Sunday, said the total shutdown of the Third Mainland Bridge would be lifted at midnight of 31st January.
- Popoola said the contractor was able to complete the repair works on the bridge on Saturday, hence the lifting of the total closure at midnight.
YOU MAY ALSO LIKE:
- Lagos, UK Sign MoU To Improve Access To Energy
- Kogi Gov Releases N3.98B For Road Projects
- Ganduje Inaugurates 2,000 COVID-19 Marshals
Ahead the stipulated day of opening the bridge, the Federal Controller of Works, Lagos, Olukayode Popoola, on Sunday, said the total shutdown of the Third Mainland Bridge would be lifted at midnight of 31st January.
According to reports Popoola told newsmen during an interview stating the contractor was able to complete the repair works on the bridge on Saturday, hence the lifting of the total closure at midnight.
He said; “The casting of the expansion joints was completed on Saturday. Therefore, the Third Mainland Bridge will be opened by midnight of Jan. 31.
“Motorists can start plying the bridge as from midnight,”.
READ ALSO: Panic As Osun Records Five New Cases Of B117 Strain Of COVID-19
EKO HOT BLOG recall that Popoola had on Wednesday 27th January, announced a three-day total shutdown of the bridge from the midnight of Friday to midnight of Monday, 1st February to allow a replacement of three expansion joints.
Popoopla said that construction works had reached the stage for casting concrete on additional three expansion joints.
According to him, there was a need to stop all movements on the bridge that could cause vibrations.
Advertise or Publish a Story on EkoHot Blog:
Kindly contact us at [email protected]. Breaking stories should be sent to the above email and substantiated with pictorial evidence.
Citizen journalists will receive a token as data incentive.
Call or Whatsapp: 0803 561 7233, 0703 414 5611